Day 6 and day 7 of the house frame construction sees the garage added on to the end of the house

Attached Image Attached Image Attached Image


And the main ridge beam for the main roof also arrived and got lifted straight off the lorry up onto the roof.

Attached Image Attached Image Attached Image Attached Image



Sadly the other shorter ridge beams for the gable ends did not arrive. They were due today but now we are told they will be here next Thursday.

Sadly that means the site will go silent for a week as they can't progress framing the roof without these other ridge beams.



Sorry to hear about the delay. That is some main ridge beam though!
  • Report
We had trouble finding that beam. The SE had specified 70mm by 400mm but nobody up here could get that (It's a Kurto beam by the way). We ended up with a 90mm by 400mm as that was all that anyone could get. It's 11.4 metres long and weighs over half a ton.

It will be supported by two internal load bearing walls as well which have yet to be installed, they have put a temporary prop under the middle of it for now.

The suppliers up here don't seem the best at customer care. It's ironic that the hard to get beam arrived first, and all the easy peasy ones have been delayed a week.

I'm looking forward to some more pictures of your own build soon.
  • Report
Jeez, that's huge! I guess it's 'Sods Law' that it's the smaller beams that have caused the delay.

Just posted my latest entry.
  • Report

May 2018

M T W T F S S
 123456
78910111213
14151617181920
212223242526 27
28293031   

Recent Entries

Recent Comments